Representative Experience

Registering a Builders Lien Against Each Parcel Under One Contract

Practice Area
Reading time
4 minute read
Year
2026
Share

A contractor that filed two claims of lien, each for the whole balance owing under one contract, and omitted its name from a numbered paragraph of the prescribed form, kept both liens on title. ATAC LAW acted for the lien claimant, and the owners' application to strike them was dismissed.

Counsel for This Matter
Mike C. Stewart, P.Eng
J.D., Q.Arb, Q.Med
Partner, Mediator, Arbitrator
Partner, Mediator, Arbitrator

Mike C. Stewart is a partner at ATAC LAW, a professional engineer, and counsel in construction disputes. He holds the…

View Profile

The Dispute

A family hired a construction company to build two houses, each with a carriage house, on a lot that was to be subdivided first. The lot was divided, the houses were largely finished, and the owners had paid the company a sum in the low seven figures. The company then registered a lien on each of the two new lots for the balance it said was still owing, and the owners wanted both off title.

The Parties’ Positions

The owners applied to strike both claims of lien and the corresponding certificates of pending litigation, sought a fine under section 45 of the Builders Lien Act, and advanced several grounds, including that the contractor had filed the liens out of time. One ground was section 16(1), which provides that a claimant under a single contract for improvements on more than one parcel “may choose to have the lien follow the form of the contract”, which the owners read as requiring one lien over both parcels. Another was the omission of the lien claimant’s name and address from the numbered paragraph of the prescribed form calling for them, the owners relying on Nita Lake Lodge Corp. v. Conpact Systems (2004) Ltd. for strict compliance with the Act.

The contractor maintained that its pleading removed any doubt about what was claimed, the notice of civil claim having put the amount at the sum of one lien and not the aggregate of the two. It relied on Coastal Building Products Div of Laurus Manufacturing and Sales Inc. v. Gill, where liens for the full amount had been filed against two properties and the pleadings had likewise clarified the sum claimed. On the form, the contractor relied on section 28(1) of the Interpretation Act, under which deviations from a prescribed form “not affecting the substance or calculated to mislead, do not invalidate the form used”. Its name and address appeared in the preamble of each form, though not in the numbered paragraph.

The Court’s Decision

The court dismissed the application, reading section 16 as permissive and declining to read the permissive “may” as the mandatory “must” merely because one lien would have made the amount claimed clearer. It observed that on other facts, where a party needed to discharge liens quickly to permit financing or a sale, filing multiple liens each for the full amount might be improper or an abuse of process.

On the form the court applied section 28(1) of the Interpretation Act, holding the omission neither material nor misleading, and distinguished the decisions where the lien claimant named did not exist. It refused the alternative request to discharge the lien from one property, having no evidence of the work done on each or the equity in either, and ordered costs in the cause. Both liens and both certificates of pending litigation stayed on title, leaving the contractor’s security for the balance intact.

Key Lessons for Lien Claimants and Owners of Multiple Parcels

  • State the amount claimed once, on the form and again in the pleading. The notice of civil claim put the claim at the amount of one lien and not the aggregate of the two, which answered any suggestion of security claimed twice.
  • Settle before filing whether to register one lien over every parcel or a separate lien against each. Section 16(1) is worded permissively, so both routes were open on this record, and a government guide describing the single-lien process does not carry the force of legislation.
  • Complete every numbered paragraph of the prescribed claim of lien form, including information already given in its preamble. The omission here was found neither material nor misleading, whereas section 28(1) gave no assistance where the lien claimant named did not exist.
  • Tender evidence of value and of the work performed on each parcel when seeking to clear a lien from one of several parcels. The court declined to apportion, having no way of knowing how much work was done on which property and no evidence of the equity in either.

The outcome of this application turned on the wording of the claims of lien, on the pleading already filed in the action, and on the material before the court when it was heard. A similar application may resolve differently.

ATAC LAW acts for owners, contractors, subcontractors and suppliers in construction disputes in British Columbia, including builders lien claims and applications to remove them from title.

Mike C. Stewart acted for the lien claimant on the application to strike the claims of lien.

More Construction Law Cases

October 6, 2026

Dismissal for Want of Prosecution After Prolonged Litigation Delay 

ATAC LAW acted for a clinic owner defending a nine-year-old construction claim in the Supreme Court of British Columbia, and the action was dismissed for want of prosecution with costs. The contractor relied on personal, business and…

Read More
September 3, 2026

Costs Cut to Half a Trial Despite a Favourable Judgement

Winning a lawsuit at trial does not guarantee recovery of its full cost. ATAC LAW acted for the construction manager awarded judgment, and the court limited its costs to half the trial after finding the property owner had substantially…

Read More
September 3, 2026

Anticipated Loss of Profit After Termination Without Cause

A contract that expressly allows termination without cause and states what that costs leaves a court little room to imply a reasonable notice term limiting lost profit. ATAC LAW acted for the construction manager, whose lost profit claim…

Read More
September 3, 2026

Overhead Records and the Quantum of a Loss of Profit Claim

Entitlement to lost profit has to be turned into a number, and the number is only as good as the records behind it. ATAC LAW acted for the construction manager at the reference, where the Registrar certified its fee but referred the profit…

Read More
September 3, 2026

The Bar for Striking a Claim Over Late Disclosure in BC

A party's late compliance with a disclosure order does not by itself meet the bar for striking its claim. ATAC LAW acted for a general contractor whose claim survived an application to strike it, though the same hearing adjourned the trial…

Read More
September 3, 2026

Where an Owner’s Budget Becomes the Measure of Lost Profit

The parties never agreed on the construction cost estimate their fee formula depended on, so the budget the owner had insisted on became the measure of lost profit. ATAC LAW acted for the construction manager, whose higher estimate was…

Read More
September 3, 2026

Staying an Earlier-Filed Action in Favour of a More Comprehensive Proceeding

Commencing an action first did not secure priority for it where the competing action covered the same contract more completely and joined every party. ATAC LAW acted for the contractor group, whose earlier action the court stayed so the…

Read More
September 3, 2026

A Delay Claim Founded on an Estimated Completion Date

An estimated substantial completion date may not support a delay claim where the contract extends that date for a stop work order or a cause beyond the manager's control. ATAC LAW acted for the owner at trial, the counterclaim was…

Read More
September 3, 2026

Reducing the Security Required to Cancel a Builders Lien

A tenant facing a builders lien for more than the claimant's evidence showed it had spent still had to post security for the full face value to clear title. ATAC LAW acted for the tenant that engaged the contractor, and the court refused…

Read More
September 3, 2026

Binding Effect of an Unsigned CCDC 17

A trade contractor's own lien, filed for nearly the full contract price, was found an abuse of process because only a fraction of that amount could realistically have been recovered

Read More