Representative Experience

Binding Effect of an Unsigned CCDC 17

Practice Area
Reading time
4 minute read
Year
2026
Share

A trade contractor's own lien, filed for nearly the full contract price, was found an abuse of process because only a fraction of that amount could realistically have been recovered

Counsel for This Matter
Mike C. Stewart
P.Eng, J.D., Q.Arb, Q.Med
Partner, Lawyer, Mediator, Arbitrator
Partner, Lawyer, Mediator, Arbitrator

Mike C. Stewart is a partner at ATAC LAW, a professional engineer, and counsel in construction disputes. He holds the…

View Mike's bio
Rodolfo Assinger
LL.B.
Associate Lawyer
Associate Lawyer

Rodolfo Assinger is a litigator at ATAC LAW whose civil practice moves fluently across construction, employment, commercial, property, estate, and…

View Rodolfo's bio

at trial; its unsigned CCDC 17 bound it by conduct alone. ATAC LAW acted for the trade contractor, which left the project a net payer after most of its claim was dismissed.

The Dispute

A formwork company took on the architectural concrete work for a multi-building residential development. The job it thought it had priced was smaller than the job the owner expected, and once other trades fell behind its crews were waiting on site instead of pouring. It billed for the difference, the owner refused, and within months it was off the site with a labour supplier suing it.

The Parties’ Positions

The trade contractor contended that its agreement was its own quotation, a scope schedule and nine pages of marked drawings, delivered the day before it mobilized and accepted by the construction manager’s email the next morning. On that footing the balcony planter walls fell outside the contract, and the additional wall contact footage it installed sounded in a claim for extras. It claimed further for unpaid progress draws, for damages for wrongful termination, and for delay measured by a window analysis setting the three months it had estimated against the eight it spent on site.

The owner submitted that the agreement was the CCDC 17 stipulated price contract its construction manager drafted after a site-trailer meeting at which the two settled both scope and price, and which the trade contractor answered by email reading “looks good”. That contract called for considerably more work, including planter walls on balconies between the ground floor and the roof of each building. The owner relied on GC 6.1.2, under which “the Trade Contractor shall not perform a change in the Work without a Change Order or a Change Directive”. It relied also on GC 6.6.1, obliging a party intending to claim to give “timely Notice in Writing of intent to claim”. It counterclaimed that the lien the trade contractor had filed against the project, in an amount approaching the entire fixed price, was an abuse of process, and claimed in the alternative under the Builders Lien Act.

The Court’s Decision

The court found the CCDC 17 to be the agreement, the trade contractor having approved it by email, raised nothing afterward, and carried on working. Work that contract contemplated could not sound in a claim for extras, and the trade contractor had not shown which wall contact footage lay outside its scope, or that it had given adequate notice. The claims for that footage, for unpaid draws and for wrongful termination were dismissed, the last on a finding of repudiation; the trade contractor recovered only on changes and rework, and on delay, reduced for overlap between the two.

The owner recovered its carrying cost on the lien funds, the lien being an abuse of process, and part of what it paid to complete the work. The awards against the trade contractor exceeded what it recovered, so it left the project a net payer, costs remaining to be spoken to.

Key Lessons for Trade Contractors and Owners

  • Treat email approval of a draft contract as execution. An unsigned contract can bind a party that approves it by email, raises nothing further, and proceeds with the work, since what the parties agreed is determined from their conduct.
  • Reconcile the scope schedule in the executed contract against the quotation before mobilizing. In this matter the work CCDC 17 contemplated could not be claimed as extra compensation, so a quotation narrower than the contract that supersedes it turns priced work into unpaid work.
  • Serve written notice of intent to claim before performing work regarded as a change. CCDC 17 requires a Change Order or Change Directive before a change in the Work, and timely written notice of intent to claim, which Canadian courts generally treat as a condition precedent to recovery.
  • Size a lien to the amount realistically recoverable in construction litigation. A lien registered in an amount disproportionate to what the claimant can reasonably hope to recover may be found an abuse of process, exposing it to the owner’s carrying cost on the funds posted to clear title.

The outcome of this matter turned on the contract the parties reached, the terms of CCDC 17 and the evidence before the Supreme Court of British Columbia at trial. A similar dispute may resolve differently.

ATAC LAW acts for owners, construction managers, trade contractors and suppliers in construction disputes at trial, in arbitration and in mediation.

More Construction Law Cases

September 3, 2026

Costs Cut to Half a Trial Despite a Favourable Judgment

Winning a lawsuit at trial does not guarantee recovery of its full cost. ATAC LAW acted for the construction manager awarded judgment, and the court limited its costs to half the trial after finding the property owner had substantially…

Read More
September 3, 2026

Anticipated Loss of Profit After Termination Without Cause

A contract that expressly allows termination without cause and states what that costs leaves a court little room to imply a reasonable notice term limiting lost profit. ATAC LAW acted for the construction manager, whose lost profit claim…

Read More
September 3, 2026

Overhead Records and the Quantum of a Loss of Profit Claim

Entitlement to lost profit has to be turned into a number, and the number is only as good as the records behind it. ATAC LAW acted for the construction manager at the reference, where the Registrar certified its fee but referred the profit…

Read More
September 3, 2026

The Bar for Striking a Claim Over Late Disclosure in BC

A party's late compliance with a disclosure order does not by itself meet the bar for striking its claim. ATAC LAW acted for a general contractor whose claim survived an application to strike it, though the same hearing adjourned the trial…

Read More
September 3, 2026

Reducing the Security Required to Cancel a Builders Lien

A tenant facing a builders lien for more than the claimant's evidence showed it had spent still had to post security for the full face value to clear title. ATAC LAW acted for the tenant that engaged the contractor, and the court refused…

Read More
September 3, 2026

Where an Owner’s Budget Becomes the Measure of Lost Profit

The parties never agreed on the construction cost estimate their fee formula depended on, so the budget the owner had insisted on became the measure of lost profit. ATAC LAW acted for the construction manager, whose higher estimate was…

Read More
September 3, 2026

Staying an Earlier-Filed Action in Favour of a More Comprehensive Proceeding

Commencing an action first did not secure priority for it where the competing action covered the same contract more completely and joined every party. ATAC LAW acted for the contractor group, whose earlier action the court stayed so the…

Read More
September 3, 2026

A Delay Claim Founded on an Estimated Completion Date

An estimated substantial completion date may not support a delay claim where the contract extends that date for a stop work order or a cause beyond the manager's control. ATAC LAW acted for the owner at trial, the counterclaim was…

Read More
September 3, 2026

Post-Judgment Interest Under a Construction Management Contract

A contract that sets its own interest rate can govern what a judgment carries after it is pronounced. ATAC LAW acted for the construction manager at the hearing that fixed interest and costs, where post-judgment interest was allowed at the…

Read More
September 3, 2026

Enforcement of a Costs Order Stayed Pending Appeal

Security for costs already held in court can support an application to stay a costs order made in the same proceeding. ATAC LAW acted for a trade contractor opposing such a stay, and the Supreme Court of British Columbia stayed the order…

Read More