The Supreme Court of British Columbia cancelled builders’ liens filed against a 132-unit Vancouver condominium development after finding that the statutory filing period had expired. In Ulmus (OKU) Development Ltd. v. Accurate Door & Hardware Company Ltd., 2026 BCSC 2174, the Court found the residences ready for their intended use no later than June 4, 2026. Disputed hardware activity after that date did not establish a later completion date.
The Project Close-Out Timeline
| Date | Event |
|---|---|
| April 15 and 28, 2026 | Occupancy permits issued for two buildings |
| June 4, 2026 | Final occupancy permit; latest completion date found by the Court |
| June 15 and July 16, 2026 | Disputed deliveries or collections of hardware |
| July 31, 2026 | Liens filed, 57 days after June 4 |
Accurate supplied doors and hardware to a three-building condominium development. No certificate of completion had been issued, and the project had no head contractor. Accordingly, section 20(2)(b) of the Builders Lien Act made completion of the improvement the relevant trigger for the 45-day filing period.
What Established the Completion Date?
Under section 1(3) of the Builders Lien Act, an improvement is completed when it, or a substantial part of it, is ready for use or being used for its intended purpose. For this development, the intended purpose was residential occupation. An occupancy permit provides evidence of readiness but does not automatically establish the completion date.
The developer’s CEO stated that the units were complete apart from minor deficiencies by June 4. The Court accepted that evidence, supported by the occupancy permits and conveyances of some units to purchasers. Justice Klein found the development ready for its intended use no later than June 4 without treating the permits alone as conclusive.
Why Later Hardware Activity Did Not Extend the Deadline
Accurate’s operations manager described materials allegedly delivered on June 15 and July 16, including doors, electric strikes and smaller hardware items. The developer disputed those deliveries and described certain materials as replacement or warranty items collected from Accurate. The Court did not resolve every disagreement about the materials.
Accurate also relied on hearsay evidence suggesting that trades continued working after June 4. However, it provided no meaningful evidence explaining how the later work or materials prevented residential use of any units. The Court found that this evidence did not undermine the developer’s account of project readiness.
Why the Court Cancelled the Liens
The Court found that the July 31 filings occurred after the 45-day statutory period had expired. It ordered cancellation under section 25 of the Builders Lien Act and awarded costs to the petitioners. It did not determine the amount owed, resolve the competing formulations of the applicable evidentiary threshold, or decide the alleged defects in the lien forms.
What Contractors and Developers Should Take From the Decision
Later deliveries, deficiency work and warranty replacements do not necessarily extend the lien-filing period. Suppliers should identify the applicable statutory deadline and preserve evidence showing how outstanding work affects an improvement’s intended use. Developers seeking cancellation should retain completion records, occupancy documents and conveyancing evidence rather than relying exclusively on permit dates.
ATAC LAW represents contractors, suppliers and developers in construction law and construction litigation. Its lawyers advise on builders’ lien filing deadlines, lien cancellation and disputed construction payments. Early assessment is important when statutory deadlines or pending property transactions require immediate action.