A cryptocurrency-mining company failed in its lawsuit against a British Columbia data-centre operator after alleging that promised hosting capacity and services were not delivered. In One Purpose Corp Limited v. DMG Blockchain Solutions Inc., 2026 BCSC 2133, the Supreme Court of British Columbia rejected claims of fraudulent misrepresentation and dishonest contractual performance. The action was dismissed despite the Court finding that DMG had breached a termination-notice requirement.
The Dispute Over Mining Capacity
In July 2019, One Purpose contracted with DMG to host 1,212 cryptocurrency miners at DMG’s Christina Lake facility, including 1,150 graphics-processing-unit (GPU) miners. One Purpose alleged that DMG had represented that all its equipment could be hosted immediately but ultimately accommodated only approximately 500 to 600 machines. DMG disputed the alleged promise and maintained that equipment defects and installation requirements affected deployment.
The agreement did not specify a deadline for connecting the miners. The facility was not a tiered hosting operation offering guaranteed uptime, and the contract distinguished hosting from separately billed maintenance and replacement parts. These distinctions were central to the Court’s assessment of DMG’s obligations.
Why the Misrepresentation Claims Failed
Justice Hoffman found that One Purpose had not proved DMG promised immediate deployment before the agreement was signed. Pre-contract communications referred to installing shelves, constructing power channels and preparing deployment schedules, while the agreement contained an entire-agreement clause. The Court also rejected a later fraud allegation arising from a September 2019 rollout schedule because One Purpose had not established that DMG lacked the intention to pursue that schedule when issued.
The initial rollout was delayed by just under two weeks, with 985 miners racked by September 30, 2019. The Court accepted evidence of certification difficulties, defective power supplies and other hardware and software problems. It did not accept that the remaining deployment difficulties established fraudulent representations about hosting capacity.
What Did “Reasonable Endeavours” Require?
Under the agreement, DMG promised to use reasonable endeavours to keep the miners supplied with electricity and internet connectivity. That wording did not guarantee uninterrupted mining or a particular financial return. The contract also excluded equipment defects from DMG’s responsibility and provided for separately chargeable maintenance services.
DMG obtained required safety certification for the equipment and performed some repairs without separate charges. One Purpose later arranged dedicated repair work directly with technicians. The Court found no breach of the four non-termination contractual provisions relied upon and noted that One Purpose had offered no evidence of industry practice for non-tiered hosting facilities.
Why the Good-Faith Claim Failed
One Purpose alleged that DMG withheld information, prioritized its own mining interests and sought to push One Purpose out of the facility. The Court was not satisfied that DMG lied or knowingly misled One Purpose about rack availability, repairs or termination. The duty of honest performance did not require DMG to disclose its internal commercial deliberations or place One Purpose’s interests ahead of its own.
The 60-Day Termination Clause Was Breached
DMG’s June 2021 termination notice incorrectly provided 15 days instead of the contractual 60 days. Justice Hoffman found that DMG failed to comply with the notice requirement, but One Purpose received additional time to relocate its equipment and assistance with packing. As no loss caused by the shortened notice was proven, the contractual breach did not result in a damages award.
One Purpose also conceded that contractual damages were subject to a limitation equivalent to three months of hosting fees, although the Court did not need to apply that cap. The action was dismissed, with the defendants presumptively entitled to costs, subject to further submissions. The decision underscores the importance of specifying deployment deadlines, service levels, maintenance fees, equipment responsibilities and termination procedures.
ATAC LAW represents businesses in commercial contract litigation and advises on corporate and commercial agreements. Its lawyers address contractual performance, risk allocation and disputes involving technology and infrastructure services.


