Expropriation Law

B.C. Court Rejects $450,000 Lease Deduction in Industrial Land Expropriation

The British Columbia Court of Appeal dismissed Metro Vancouver’s attempt to reduce compensation for expropriated waterfront industrial land by $450,000. The Court rejected the argument that the assessed value of a tenant’s leasehold interest must automatically be deducted from the market value of the landowner’s interest.

In Greater Vancouver Sewerage and Drainage District v. S & R Sawmills Ltd., 2026 BCCA 422, the Court upheld the trial judge’s valuation approach, leaving intact a property valuation reported at approximately $39.54 million.

The decision clarifies how existing leases affect compensation for expropriated commercial and industrial property, particularly where ownership and leasehold interests are held by different parties.

Industrial Land Expropriated for Wastewater Infrastructure

On March 12, 2021, the Greater Vancouver Sewerage and Drainage District expropriated a 15.05-acre property owned by S & R Sawmills Ltd. near the Golden Ears Bridge. The land was required for construction and expansion of the Northwest Langley Wastewater Treatment Plant.

Part of the property was leased to Mainland Sand and Gravel, which used the site to store, process and ship sand and gravel dredged from the Fraser River.

At the expropriation date, the lease had approximately nine and a half months remaining. It was non-assignable, provided no right of renewal and generated more than $700,000 annually in rental income, plus triple-net cost recovery. The parties could nevertheless negotiate an extension by mutual agreement.

The District had paid Mainland approximately $490,000 for its leasehold interest. It argued that $450,000, representing the assessed value of the tenant’s rental advantage, should be deducted from compensation payable to S & R.

The trial judge rejected that deduction, and the District appealed.

Why the Lease Value Was Not Automatically Deducted

Under sections 31 and 32 of British Columbia’s Expropriation Act, compensation is determined by reference to the market value of the owner’s estate or interest in the expropriated land. Where multiple interests exist, their values must be established separately if practical.

The District argued that this required the tenant’s leasehold value to be calculated and subtracted from the owner’s compensation.

The Court of Appeal disagreed.

The proper question was what a willing purchaser would have paid for S & R’s ownership interest, subject to the lease, on the expropriation date. The tenant’s leasehold value was relevant only to the extent that the lease affected the market value of the owner’s interest.

A lease could increase, decrease or have no material effect on that value, depending on its terms and the property’s characteristics.

Why the Court Accepted the Appraisal Evidence

The competing appraisals assessed the property’s highest and best use as industrial development land. Both relied on comparable property sales to establish a value per acre rather than primarily using rental income.

None of the comparable properties was leased, making the effect of Mainland’s tenancy a separate valuation question.

S & R’s appraiser considered the remaining lease income potentially beneficial but did not increase the valuation because of it. Instead, the appraiser treated the lease as neutral, finding that the property’s industrial development value was the principal determinant of market value.

The trial judge accepted that evidence, and the Court of Appeal found no legal error in doing so.

The Court also clarified that a non-assignable lease can still have market value.

Implications for Expropriated Commercial Property

The decision confirms that compensation for leased property cannot be calculated simply by subtracting a tenant’s separately assessed leasehold value from the owner’s interest.

For commercial and industrial landowners, valuation evidence should address the actual effect of a lease on market value, including its remaining term, rental income, renewal and assignment rights, and the property’s highest and best use.

The central question is how those characteristics would influence a purchaser’s assessment of the owner’s interest, rather than the independent value attributed to the tenant’s lease.

ATAC LAW represents commercial and industrial property owners, landlords and businesses in British Columbia expropriation and compensation disputes, including contested valuations and infrastructure-related land acquisitions.

Related content

More legal insights and practical guidance from our team.

View all
builder lien holdback construction payment dispute Construction Law

Provincial Court is No Place for Builders Lien Claims

The British Columbia Court of Appeal overturned orders striking construction payment claims and staying a separate builders-lien holdback claim because of overlapping…

Mike Stewart, P.Eng., Partner, Construction Lawyer, Mediator & Arbitrator
Patullo bridge engineering arbitration Surrey, BC Construction Law

Pattullo Bridge Arbitration: B.C. Court Refuses Appeal of $4.94 Million Design Award

The British Columbia Court of Appeal refused a contractor’s application to appeal an arbitration award arising from engineering design errors on the…

Mike Stewart, P.Eng., Partner, Construction Lawyer, Mediator & Arbitrator
bc dam repair liability Commercial Real Estate and Disputes

Court Rules Province Had No Duty to Warn Property Buyers of Alleged Dam Defects

The British Columbia Court of Appeal upheld the striking of a negligence claim against the Province for allegedly failing to warn property…

Mike Stewart, P.Eng., Partner, Construction Lawyer, Mediator & Arbitrator