The B.C. Supreme Court declared 39 presale agreements unenforceable after material changes affecting the Lumina Eclipse development were not disclosed to purchasers as required under the Real Estate Development Marketing Act. The decision has important implications for developers, lenders, insolvency professionals and purchasers involved in presale developments.
In KingSett Mortgage Corporation v. Lumina Eclipse Limited Partnership, 2026 BCSC 1598, the Supreme Court of British Columbia considered the consequences of failing to update a disclosure statement as significant financial, construction and regulatory problems developed over the course of a presale project. The Court declared 39 presale agreements, representing approximately $30.5 million in purchase prices, unenforceable against the purchasers. By the time the applications were heard, the Burnaby development had been completed, an occupancy permit had been issued and the project was being administered under the Companies’ Creditors Arrangement Act (CCAA). Neither eventual completion nor the CCAA proceeding displaced the consequences of the earlier disclosure failures.
The decision provides important guidance on three related issues. A developer’s disclosure obligations under the Real Estate Development Marketing Act (REDMA) can continue after a presale agreement has been signed. Materiality is assessed when the disclosure obligation arises rather than with hindsight after the project has recovered or been completed. A subsequent restructuring proceeding does not necessarily restore the enforceability of agreements already affected by pre-filing statutory non-compliance.
For participants in B.C. development projects, the broader significance extends beyond the particular purchasers before the Court. REDMA compliance can affect the enforceability of presale receivables, the assumptions underlying project financing, the administration of a distressed development and a purchaser’s obligation to complete.
Why Lumina Eclipse Matters
Presale disclosure is sometimes treated primarily as a marketing or regulatory requirement arising at the beginning of a development. Lumina Eclipse demonstrates the risk in that approach. The disclosure record must remain responsive to material developments that arise while purchasers remain entitled to disclosure under REDMA. A serious event affecting construction, project financing, warranty coverage, permitting or expected completion can therefore create more than an operational problem. It may also require the developer to reconsider the accuracy of its existing disclosure statement.
The consequence of failing to do so can be substantial. Section 23 of REDMA can make a purchase agreement unenforceable against a purchaser following a breach of Part 2 of the legislation. In Lumina Eclipse, that consequence was not reversed simply because the building was eventually completed.
The decision therefore links disclosure compliance directly to project value. Presale agreements may form an important part of a development’s expected revenue, financing structure or restructuring strategy. Their value cannot necessarily be separated from the statutory compliance history supporting them. That makes the decision relevant not only to developers and purchasers, but also to lenders and insolvency professionals whose decisions may depend upon the expected completion of existing presales.
What Happened at Lumina Eclipse
Lumina Eclipse is a condominium development in Burnaby. The developer filed its initial disclosure statement in September 2021. Purchasers entered into presale agreements between 2021 and 2023. The disclosure materials described a project under construction, supported by new home warranty insurance and expected to complete within an identified period.
The project subsequently encountered a series of significant difficulties. In June 2023, the Canada Revenue Agency obtained a judgment of approximately $12 million against the developer and registered it against title. In October 2024, the provider of the project’s new home warranty suspended coverage for non-payment of premium. The following month, the City of Burnaby suspended the building permit and construction stopped.
On January 8, 2025, the Court granted an initial order under the CCAA after the senior secured lender commenced the restructuring proceeding. The following day, the regulator raised concerns about the project’s REDMA disclosure. The project eventually resumed. Construction was substantially completed in March 2026, followed by an occupancy permit in April. Purchasers were then called upon to complete their transactions at the prices agreed several years earlier.
The issue before the Court was not simply that the project had experienced difficulty. The central problem was that material developments had occurred without the disclosure record being amended as required.
Continuing Disclosure Under REDMA
REDMA regulates the marketing of development units in British Columbia. Its disclosure regime does not necessarily end once a purchaser has signed a presale agreement. Section 16 requires a developer that becomes aware of prescribed non-compliance or a misrepresentation in a disclosure statement to take the steps required by the legislation. Depending on the nature of the change, that may require an amendment or a new disclosure statement. The required disclosure must also reach purchasers who remain entitled to receive it.
In Lumina Eclipse, developer awareness was not seriously contested. The Court considered the relevant events significant enough that the developer was unlikely to have been unaware of them at or around the time they occurred. The decision therefore reinforces the importance of connecting what happens on a project with the legal disclosure record maintained for the development.
The personnel who first learn about a suspended permit, missed warranty premium, construction shutdown, financial judgment or revised completion schedule may sit within construction, finance or project management rather than the team responsible for REDMA compliance. That organizational separation does not reduce the statutory significance of the event. A functioning disclosure process needs information to move across those functions before the gap between project reality and the filed disclosure statement becomes material.
What Constituted a Material Fact
Justice Masuhara found that several undisclosed developments qualified as material facts under REDMA. They included the judgment registered against title, suspension of warranty coverage, suspension of the building permit, cessation of construction and the failure to update the disclosed completion schedule. The significance lies not simply in the number of events. Together, they described a project materially different from the project presented in the existing disclosure record.
The Court applied an objective assessment of materiality. The inquiry did not depend on proving that a particular purchaser personally would have refused to buy had the information been disclosed. The decision also does not mean that every project change or technical omission automatically makes a presale agreement unenforceable. REDMA distinguishes material information from immaterial or technical deficiencies.
The more useful question for project participants is therefore not simply if something changed. The question is what the change meant at the time it arose for the development, its value, price, use, viability or expected completion. That timing matters.
Materiality Is Not Determined With Hindsight
One of the most important aspects of Lumina Eclipse is the Court’s treatment of later project completion. By April 2026, the tower was complete enough for an occupancy permit to be issued. The circumstances that had previously interrupted the project had therefore changed substantially by the time purchasers were called upon to close. That did not erase the earlier disclosure problem.
The Court assessed materiality by reference to the circumstances existing when disclosure was required. A project event does not cease to have been material merely because the development later recovers from it. This distinction is particularly important on distressed projects.
A suspended building permit may later be reinstated. Warranty coverage may be restored. Construction may resume. Financing may be reorganized. A delayed development may ultimately obtain occupancy. Those later developments may be commercially significant, but they do not necessarily answer the earlier REDMA question. If disclosure was required when the material event occurred, later success does not by itself rewrite the compliance history.
The practical consequence is that a developer should not postpone the disclosure analysis on the assumption that the underlying problem may soon be corrected.
Enforceability Under Section 23
Section 23 of REDMA addresses the enforceability of purchase agreements following non-compliance with Part 2 of the legislation. The distinction between unenforceability and rescission is important. The Court did not treat the agreements as automatically void, cancelled or terminated. Instead, section 23 operated to prevent enforcement of the agreements against the affected purchasers.
That distinction became especially important because Lumina Eclipse was already subject to a CCAA proceeding. The respondents argued that the restructuring orders and stay should prevent the purchasers from obtaining the declarations they sought. The Court rejected that position.
Justice Masuhara treated section 23 as operating as a defence to enforcement rather than as a separate remedial claim against the debtor. The relevant REDMA breaches had also occurred before the CCAA proceeding began. The CCAA could govern the administration of the insolvent companies, control proceedings and stay remedies. It did not, on the Court’s analysis, convert purchase agreements already affected by REDMA non-compliance into enforceable contracts.
REDMA and the CCAA Serve Different Functions
The interaction between REDMA and the CCAA was one of the most significant aspects of the decision. The CCAA gives supervising courts broad authority to manage restructurings, preserve enterprise value and balance stakeholder interests. Those powers can include stays of proceedings as well as control over the exercise of legal rights.
REDMA addresses a different subject. Its disclosure regime governs the conditions under which a developer markets development units and enforces resulting purchase agreements against purchasers. The Court concluded that the two statutory schemes could operate together in this case.
The doctrine of federal paramountcy did not change that result. A reduction in value available to the restructuring estate did not itself establish the type of conflict required to displace the provincial legislation. That conclusion has consequences for distressed developments supported by significant presale revenue.
A restructuring strategy may assume that purchasers can be required to complete once construction is finished. Lumina Eclipse demonstrates that the enforceability of those agreements may first depend upon events that occurred long before the restructuring commenced. For insolvency professionals, lenders and other stakeholders, the disclosure history can therefore become part of the underlying asset analysis.
The Decision Did Not Determine Deposit Entitlement
The declaration that the agreements were unenforceable did not resolve every financial consequence arising from the presales. In particular, the Court did not decide the purchasers’ entitlement to recover their deposits in the same hearing. This distinction is important.
The Lumina Eclipse development had used a deposit protection facility that allowed purchaser deposits to be applied toward construction financing. By the time the enforceability applications were heard, a substantial portion of the deposits collected for the development was no longer being held in trust. The Court directed the deposit issues to a further hearing.
An unenforceable purchase agreement therefore does not necessarily mean that a deposit is immediately returned. Deposit recovery can raise separate questions concerning trust funds, insurance arrangements, secured claims and the administration of an insolvency proceeding. For purchasers, the result under section 23 answers the developer’s ability to compel completion. The financial treatment of the deposit may require a separate analysis.
What the Decision Means for Developers
For developers, Lumina Eclipse reinforces the need to treat REDMA disclosure as an ongoing project function rather than a document completed at the start of marketing. Material developments frequently become known first through construction reports, lender communications, municipal correspondence, warranty providers or financial records.
A developer should have a process that connects project, construction, finance and legal teams so significant events reach the person responsible for the disclosure record. Events such as a permit suspension, loss of warranty coverage, material construction stoppage, significant liability registered against title or substantial change in the expected completion schedule should trigger a prompt review of the disclosure statement.
The purpose is not to assume that every adverse event requires an amendment. It is to ensure the question is considered when the event occurs, with the basis for the decision properly recorded. Waiting to see if the project recovers can create a different risk. By the time the underlying difficulty is corrected, the disclosure obligation may already have arisen.
What the Decision Means for Lenders
For lenders financing presale developments, the decision raises a due diligence issue that extends beyond conventional security review. Presale receivables may form part of the expected source of repayment, project valuation or exit strategy. Their economic value can depend upon the enforceability of the underlying purchase agreements.
A lender relying materially on future presale closings should therefore consider the disclosure statement and amendment history as part of project diligence. The issue becomes particularly important when the development has experienced events such as permit problems, warranty interruption, prolonged construction delays or serious financial distress.
In those circumstances, the question is not simply how many presales remain outstanding or the aggregate value of their contract prices. The compliance history supporting those agreements may also affect their realizable value. For a lender entering a distressed situation after many of the relevant events have already occurred, that history may not be apparent from the loan documents or registered security alone.
What the Decision Means for Insolvency Professionals
Insolvency professionals administering a development should not assume that CCAA protection can restore contractual enforceability affected by pre-filing statutory non-compliance. The timing of the alleged REDMA breach can be critical. Where material disclosure failures predate the restructuring, the validity of a completion strategy may depend in part on rights created under another statutory regime before the CCAA process began.
That makes early review of the disclosure history important. The same care should extend to communications with purchasers. A court-appointed officer may inherit a project with a complicated history, incomplete disclosure or significant changes that occurred before its appointment. Understanding what purchasers received, when they received it and how the project changed can be important before taking a position on completion obligations.
The decision does not remove the broad supervisory powers available under the CCAA. It does show that those powers operate within a wider statutory environment.
What the Decision Means for Purchasers
Purchasers should retain the disclosure statement provided when they entered into the presale agreement, together with every subsequent amendment received before completion. Significant changes in permits, warranty coverage, construction progress, financing or the projected completion of a development may warrant closer examination of the disclosure history.
The existence of a problem does not itself establish unenforceability. The analysis depends on the statutory requirements, the materiality of the event, the disclosure actually made and the timing of that disclosure.
Purchasers should also distinguish their obligation to complete from their entitlement to recover a deposit. Lumina Eclipse illustrates that those questions can proceed separately. A declaration that an agreement cannot be enforced against a purchaser does not necessarily determine where the deposit is held, which parties may have claims to it or the process required for recovery.
What Remains Unsettled
Lumina Eclipse provides substantial guidance, but it does not resolve every issue arising under section 23. One question concerns the temporal language used in section 23 and the extent to which post-contract developments can make an existing purchase agreement unenforceable. The Court treated the wording of the statutory provisions as supporting a continuing consequence for failures arising after the agreement was signed.
The relationship between that interpretation and earlier appellate authority may receive further consideration in a future case. In Woo v. Onni Ioco Road Five Development Limited Partnership, 2014 BCCA 76, the Court of Appeal considered the objective significance required for a fact to be material under REDMA. The precise interaction between that framework and the reasoning in Lumina Eclipse may matter most in cases involving changes closer to the margins of materiality.
A further issue concerns the boundary between REDMA rights and the supervisory powers available in an insolvency proceeding. In Lumina Eclipse, the Court concluded that the reduction in value available to the estate did not create an operational conflict between REDMA and the CCAA. A future case presenting a different restructuring record may test the limits of that conclusion.
These unresolved questions do not diminish the immediate significance of the decision. They make careful analysis of the facts, disclosure history and timing even more important.
The Broader Compliance Lesson
The central lesson from Lumina Eclipse is not that every distressed development produces unenforceable presale contracts. It is that the disclosure record needs to move with the project. A material fact does not produce the section 23 consequence merely because it exists. The problem arises when the disclosure required by REDMA is not made.
That creates a practical point for every participant whose position depends upon presale agreements. Developers need a mechanism for identifying material changes as they occur. Lenders should consider REDMA compliance when assessing presale receivables. Insolvency professionals need to understand the disclosure history inherited with a distressed project. Purchasers should preserve the disclosure record and examine material changes that occurred before title passed.
Lumina Eclipse shows how those issues can converge on a single development. What begins as a change in construction, finance or project administration can ultimately affect contractual enforceability, restructuring strategy and the allocation of significant financial risk.
ATAC LAW advises developers, lenders, insolvency professionals and purchasers on disputes involving real estate developments, presale agreements and REDMA. Where a project raises questions about disclosure obligations or the enforceability of a purchase agreement, the analysis begins with the disclosure record, the events affecting the development and the timing of the statutory obligations engaged.
